Skip to content
ServerCalc ServerCalc
Power & Energy

NVIDIA Server Rack Power Consumption Calculator

What a GB200 NVL72, a GB300 NVL72 or a rack of DGX systems actually draws, and what your facility needs to feed it.

Inputs

Equipment in the rack

Loads a ready-made rack. Every line stays editable.

Draw comes from the calibrated power model, not a PSU label.

50%

Applied to servers added from here on.

EquipmentQtyU eachW eachkg each
GB200 compute tray (2 Grace + 4 B200)
GB200 NVLink switch tray
33 kW power shelf (6 x 5.5 kW)
Coolant manifold + busbar assembly
Total U / Total W35U122,2501,182
Rack & floor

What the facility will actually deliver to one cabinet.

kg

Static load your floor takes per rack footprint.

Power feed

A+B doubles the circuits: each side must carry the rack alone.

Operating cost
$

Your blended rate per kWh, taxes included.

Facility overhead multiplier. 1.0 counts IT load only.

  • Peak draw of 164000 W needs 5 circuits at 35503 W usable each, so provision 10 with your chosen feed redundancy.
  • Peak draw of 164.0 kW exceeds the 132.0 kW this rack is allocated. Either the facility raises the feed, or equipment comes out.
Results update live as you type.

Results

Rack power draw
122.25 kW
164.00 kW peak · 3493 W per U
First limit reached
Power budget
0% headroom left before it binds.
Rack space used
35U / 48U
13U free of 48U.
Loaded weight
1,432 kg
3,157 lb, including the cabinet.
Current draw
173.5 A
232.8 A at peak, 415 V Three-phase.
Circuits needed
5
10 to provision with Dual A+B feed.
Heat output
417,134 BTU/hr
Cooling required
34.76 tons
Annual energy
1,070,910 kWh
Energy cost per year
$240,955
Cost per U per year
$6884.42

Rack elevation

35U / 48U

Laid out bottom-up, heaviest first, which is how a rack is actually built and what keeps its centre of gravity low. Empty space at the top is real: almost no rack fills to 42U before power or weight stops it.

48454035302520151051U1: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U2: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U3: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U4: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U5: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U6: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U7: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U8: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U9: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U10: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U11: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U12: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U13: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U14: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U15: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U16: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U17: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U18: GB200 compute tray (2 Grace + 4 B200) · 6100 WGB200 compute tray (2 Grace + 4 B…U19: 33 kW power shelf (6 x 5.5 kW) · 150 W33 kW power shelf (6 x 5.5 kW)U20: 33 kW power shelf (6 x 5.5 kW) · 150 W33 kW power shelf (6 x 5.5 kW)U21: 33 kW power shelf (6 x 5.5 kW) · 150 W33 kW power shelf (6 x 5.5 kW)U22: 33 kW power shelf (6 x 5.5 kW) · 150 W33 kW power shelf (6 x 5.5 kW)U23: 33 kW power shelf (6 x 5.5 kW) · 150 W33 kW power shelf (6 x 5.5 kW)U24: 33 kW power shelf (6 x 5.5 kW) · 150 W33 kW power shelf (6 x 5.5 kW)U25: 33 kW power shelf (6 x 5.5 kW) · 150 W33 kW power shelf (6 x 5.5 kW)U26: 33 kW power shelf (6 x 5.5 kW) · 150 W33 kW power shelf (6 x 5.5 kW)U27: GB200 NVLink switch tray · 1250 WGB200 NVLink switch trayU28: GB200 NVLink switch tray · 1250 WGB200 NVLink switch trayU29: GB200 NVLink switch tray · 1250 WGB200 NVLink switch trayU30: GB200 NVLink switch tray · 1250 WGB200 NVLink switch trayU31: GB200 NVLink switch tray · 1250 WGB200 NVLink switch trayU32: GB200 NVLink switch tray · 1250 WGB200 NVLink switch trayU33: GB200 NVLink switch tray · 1250 WGB200 NVLink switch trayU34: GB200 NVLink switch tray · 1250 WGB200 NVLink switch trayU35: GB200 NVLink switch tray · 1250 WGB200 NVLink switch trayFree · 13U
  • Rack-scale AI122,250 W

Three budgets, one rack

Rack units, kilowatts and kilograms run out at different times, and the one that stops you is rarely the one being watched. A 42U cabinet physically holds 21 2U servers; a 10 kW feed powers about six of them.

100%

About this calculator

NVIDIA rack power is a different question from ordinary rack power, because on the rack-scale systems the rack is the product. A GB200 NVL72 is not seventy-two servers you install in a cabinet. It is one machine, 48U tall, delivered as a rack, with no per-server power supplies at all: eight power shelves convert facility AC onto a shared 50 V DC busbar, and 18 compute trays plus 9 NVLink switch trays draw from it.

So this calculator opens on a real GB200 NVL72, built tray by tray. Switch the preset for a GB300 NVL72, a rack of DGX B200s, a rack of DGX H100s, or air-cooled HGX nodes, and every line stays editable if your configuration differs.

The numbers are the story. A well-filled traditional rack of 2U servers runs around 12 kW. A GB200 NVL72 draws about 120 kW in one cabinet, and peaks well above that. That is ten conventional racks of power in a footprint of roughly 0.64 square metres, which is why these systems are mandatory direct-to-chip liquid cooled, sit on slab floors rather than raised tiles, and arrive with their own coolant manifolds.

Three things make NVIDIA racks catch people out, and the calculator surfaces all three:

  • Peak is a long way above nominal. NVIDIA quotes the GB200 NVL72 near 120 kW and HPE at 132 kW nominal, but the electrical design peak runs to roughly 155 to 192 kW. Feeds, breakers and upstream capacity get sized on the peak, not the average.
  • Weight. A loaded NVL72 is around 1.4 tonnes. A standard raised floor tile is rated near 570 kg. These racks go on slab, and the delivery route needs checking before the crate arrives.
  • The heat has nowhere to go without liquid. 120 kW is about 410,000 BTU/hr, or 34 tons of cooling, from one cabinet. No amount of air handles that.

The formula

Rack-scale systems are summed at the tray level, which is how they are actually built:

rack watts = (compute trays × W each) + (switch trays × W each) + (power shelves × standby)

For a GB200 NVL72 that is 18 compute trays, 9 NVLink switch trays and 8 power shelves in a 48U frame. Each compute tray carries two Grace CPUs and four Blackwell GPUs, so 18 trays give the 36 Grace and 72 Blackwell the name refers to.

The tray figures here are AC-side: the power shelves' conversion loss is already inside them, so the shelves themselves contribute only standby draw rather than being counted twice. That matters because unlike a conventional server there is no per-node PSU efficiency to apply, the conversion happens once at the shelf.

Facility side

amps = watts ÷ (√3 × volts × PF) for the three-phase feeds these racks require
usable circuit watts = √3 × volts × amps × 0.8 × PF
circuits = ceil(peak watts ÷ usable circuit watts), doubled for A+B

At 415 V three-phase a 63 A circuit delivers about 35 kW usable after the 80% continuous-load derate. A 120 kW NVL72 therefore needs four to five such circuits, or eight to ten once you provision redundant A and B feeds, each sized to carry the whole rack alone.

Heat

BTU/hr = watts × 3.412 and tons = BTU/hr ÷ 12,000

On an NVL72 the great majority of that leaves through the coolant loop rather than the air. HPE's figures for their GB200 NVL72 split it roughly 115 kW liquid to 17 kW air, so the room still needs air handling for the residue even though the rack is liquid cooled. A CDU, in-row or facility-provided, sits between the rack loop and the building water.

Where the DGX figures differ

DGX systems are conventional servers with their own power supplies, so they go through the same component model as everything else on this site and report a realistic sustained peak. NVIDIA separately publishes a maximum system power rating, which is the nameplate ceiling: 6.5 kW for the DGX A100, 10.2 kW for the DGX H100 and H200, and 14.3 kW for the DGX B200. Size the electrical feed on NVIDIA's published maximum; use the modelled figure for energy, cost and heat, which is what the machine actually spends its life drawing.

Common use cases

  • Working out what a GB200 or GB300 NVL72 draws before committing a data hall to it
  • Sizing three-phase feeds and A+B circuits for an AI rack
  • Checking floor loading before a 1.4 tonne rack is delivered
  • Getting the liquid and air cooling split for a CDU specification
  • Comparing a rack of DGX B200 against an NVL72 on kW per rack
  • Costing an AI row per year at your electricity tariff
  • Explaining to a facilities team why 120 kW cannot be air cooled
  • Planning how many AI racks a given substation or UPS capacity supports

Frequently Asked Questions

How much power does a GB200 NVL72 rack use?
About 120 kW nominal by NVIDIA's figure, with HPE quoting 132 kW for their build and an electrical design peak in the region of 155 to 192 kW. The rack holds 18 compute trays (two Grace CPUs and four Blackwell GPUs each), 9 NVLink switch trays and 8 power shelves of 33 kW apiece in a 48U frame. Size the facility feed on the peak rather than the nominal: the gap between them is 30 to 60 kW, which is several conventional racks' worth of headroom you either have or do not.
How much power does a GB300 NVL72 need?
Roughly 132 kW nominal, quoted up to about 142 kW, with an electrical design peak near 155 kW. Same architecture as the GB200 NVL72: 18 compute trays, 9 NVSwitch trays, 8 power shelves, 48U, 600 mm wide. One notable change is that NVIDIA added capacitor-based energy storage to the GB300 power shelves specifically to smooth the power transients that GB200 deployments exposed, charging during low GPU demand and discharging during spikes so the facility sees a steadier draw.
How many circuits does an NVIDIA AI rack need?
At 415 V three-phase, a 63 A circuit delivers about 35 kW usable after the 80% continuous-load derate. A 120 kW NVL72 therefore needs four to five circuits, and eight to ten once you provision redundant A and B feeds, because each side must be able to carry the entire rack on its own. Note that inside the rack there are no per-server power cords: the power shelves feed a common busbar, so the facility connection is a small number of high-current three-phase feeds rather than dozens of C13s.
Can a GB200 NVL72 be air cooled?
No. Direct-to-chip liquid cooling is mandatory, not an option. At roughly 120 kW in a 0.64 square metre footprint the rack produces around 410,000 BTU/hr, about 34 tons of cooling, which no air path can carry. Most of the heat leaves through the coolant loop; HPE's figures for their GB200 NVL72 split it approximately 115 kW liquid to 17 kW air, so the room still needs air handling for the remainder. Between the rack and the building water sits a CDU, either rack-integrated, in-row or facility-provided.
How much does an NVIDIA NVL72 rack weigh?
Around 1.4 tonnes fully populated, roughly 3,000 lb. That is well beyond the 570 kg a standard raised floor tile is commonly rated for, so these racks go on slab floors or require a structural assessment and spreader plates. Check the delivery route too: the floor loading of the loading bay, the freight lift capacity, and any ramp or threshold between them. The calculator flags the floor limit as soon as you exceed it.
How much power does a DGX B200 use?
NVIDIA rates the DGX B200 at 14.3 kW maximum system power, and it is a 10U chassis with eight B200 GPUs. That published figure is the nameplate ceiling you size an electrical feed against; realistic sustained peak is closer to 12 to 13 kW, and idle is around 2.6 kW. Four DGX B200s in a rack come to roughly 50 kW sustained and 57 kW at nameplate, which already needs three-phase distribution and either rear-door heat exchangers or containment.
How much power does a DGX H100 or H200 use?
Both are rated at 10.2 kW maximum system power in an 8U chassis with eight SXM GPUs. Modelled sustained peak is around 8.1 kW with idle near 1.8 kW, so a rack of four is roughly 28 kW in normal operation and 41 kW at nameplate. The H200 has the same power envelope as the H100 despite carrying more and faster memory, which is the point NVIDIA makes about that generation: more performance inside the same power budget.
How many DGX systems fit in one rack?
Space says five DGX H100s in 42U or four DGX B200s in 48U. Power usually says fewer. Four DGX B200s alone are about 57 kW at nameplate, which is past what most colocation cabinets will deliver and well past what air cooling handles without rear-door heat exchangers. In practice DGX deployments are power-limited and often ship two to four per rack, which is why NVIDIA's SuperPOD reference designs specify the rack layout and the facility feed together rather than leaving it to be worked out afterwards.
What is the difference between HGX, DGX and NVL72?
HGX is the GPU baseboard NVIDIA sells to server makers: Dell, HPE, Supermicro and others build it into their own chassis, and those systems appear in this site's other rack calculators. DGX is NVIDIA's own complete server, a conventional rackmount box with its own power supplies. NVL72 is rack-scale: NVIDIA delivers an entire 48U rack as one machine with a shared busbar, shared liquid loop and a single NVLink domain across all 72 GPUs. Power planning differs at each level, which is why this calculator handles trays, whole DGX nodes and OEM HGX systems separately.
Why is peak power so much higher than the quoted rack power?
Because AI training workloads are synchronous. Thousands of GPUs step through the same training iteration together, so they all ramp to full power at the same instant and all drop together at a checkpoint or all-reduce. That produces power transients far sharper than anything a conventional server room sees, and it is why the electrical design peak for an NVL72 sits tens of kilowatts above nominal. NVIDIA added capacitor energy storage to the GB300 power shelves specifically to absorb those swings before they reach the facility. Size your feed, UPS and upstream capacity on the peak figure.
How much does it cost to run an NVIDIA AI rack for a year?
At 120 kW running continuously that is about 1,050 MWh a year of IT load. At $0.15 per kWh that is roughly $158,000 a year for one rack before cooling overhead, and applying a PUE of 1.5 takes it past $235,000. Cooling efficiency matters enormously at this density: dropping from PUE 1.5 to 1.15 on a single NVL72 saves about $55,000 a year, which is one reason liquid-cooled AI facilities are being built to much tighter PUE targets than traditional halls.

Spot an error? Have feedback?

Tell us what is wrong with the math, what is missing, or which server model you would like added. We read everything.